Why have I received more than one party wall notice?

Because one project can involve more than one kind of notifiable work, and each kind has its own notice. A rear extension, for example, often brings a line of junction notice and an excavation notice together.

Common combinations

Project next door Notices you may receive
Rear extension on the boundary Line of junction (section 1) and adjacent excavation (section 6)
Loft conversion Party structure (section 3)
Kitchen extension tied into the house Party structure and adjacent excavation
Basement Adjacent excavation, often with party structure

Reply to each one

Each notice needs its own answer within 14 days. You can deal with them all in one letter, provided it is clear which notice each answer refers to. Our reply form produces a reply for each type.

Can my answers differ?

Yes. You might be relaxed about a new boundary wall but want a surveyor for digging close to your house. In practice, if you appoint a surveyor for one notice, it usually makes sense for them to deal with all of them.

Duplicates

Sometimes the same notice arrives twice, once by post and once by hand. Compare the dates and contents; if they are identical, one reply covers both.

Common questions

Do I need a separate surveyor for each notice?

No. One surveyor can deal with every notice arising from the same project.

One notice came weeks after the other. Is that allowed?

Yes. Each notice has its own timetable from the day it is served.

Where this comes from in the Act

Links go to the official text of the Party Wall etc. Act 1996 on legislation.gov.uk.